SunSirs--China Commodity Data Group

Sign In

Join Now

Contact Us

Home > BDO News > News Detail
BDO News
SunSirs: Domestic situation BDO manufacturers on March 11
March 11 2022 10:53:56()


The 30000 ton and 100000 ton BDO units of Shaanxi Shanhua Chemical Co., Ltd. operate stably. BDO is mainly for its own use, and the sales volume outside the spot is limited. No offer is made for the time being.

Shaanxi Heimao BDO plant with a capacity of 60000t / a operates normally. There is no quotation in stock.

Shaanxi Ronghe 60000t / a BDO unit has a load of 70%, all of which execute the long-term contract, and there is no spot sales for the time being.

Xinjiang Meike phase I 60000 T / A, phase II 100000 t / A and phase III 100000 t / a units operate stably, execute long-term contracts on a monthly basis, and have no spot sales.

Xinjiang Tianye 30000 ton unit and three sets of 60000 ton units are in operation, with an overall load of 70%, and there is no spot quotation for the time being.

The BDO unit with a capacity of 60000 tons / year in Xinye, Xinjiang is scheduled to be overhauled on February 25. It is expected to take five days. There is no quotation in stock.

Xinjiang Guotai Xinhua 200000 t / a BDO production capacity device operates stably, and there is no quotation in stock.

Panjin Changchun 150000 T / a BDO plant operates normally, mainly under the BDO main supply contract, and there is no quotation for the spot.

Sichuan Tianhua BDO 25000 ton phase I and 60000 ton phase II units are in normal operation. BDO is mainly used by downstream PTMEG and GBL, and there is no external quotation.

Fuhua industry and trade (Meizhou Bay, Fujian) shut down the 40000 t / a BDO unit in early October and shut down the relocation equipment on October 15. The relocation project includes 36000 T / a BDO unit and 60000 T / a PBT unit. The BDO and PBT capacity after relocation is consistent with the existing project.

Yizheng Dalian BDO plant with a capacity of 50000 T / a operates normally. BDO will not quote for long-term contract orders.

Chongqing Chiyuan chemical BDO plant with a capacity of 60000 tons / year is running smoothly. It is used for downstream PTMEG and will not be quoted for external use.

The 100000 ton unit of Inner Mongolia Dongyuan Technology Co., Ltd. operates normally. At present, all of them implement the long-term contract and have no spot sales.

The two sets of BDO units with a capacity of 100000 t / a of Sinopec Great Wall energy and Chemical Co., Ltd. operate stably, and the downstream PTMEG operates with a slight reduction in load, and the spot quotation is not available for the time being.

Henan crane coal has a capacity of 100000 / year, and the BDO unit is in normal operation. At present, the main supply contract orders are dominated, and there is no offer in stock, but the actual order is negotiated.

Henan Kaixiang auctioned 99 tons of BDO at 3 p.m. on March 10. The starting price was 28800, and the final transaction was 66 tons 28800 and 33 tons 28850 (apron, yuan / ton, accepted and delivered).

If you have any questions, please feel free to contact SunSirs with support@sunsirs.com. 

Exchange Rate:

8 Industries
Energy
Chemical
Rubber & Plastics
Textile
Non-ferrous Metals
Steel
Building Materials
Agricultural & Sideline Products